Repowering Würzburg - From old to new:

Construction of a new processing plant and renewal of the storage areas

Blue Phoenix Deutschland GmbH is modernising its recycling plant for ash from thermal waste treatment plants in the industrial park of the New Würzburg Port. The aim is to significantly improve economic efficiency, environmental and health protection, and emission reduction. 

Am 20.10.2026 fand an dieser Stelle eine Online-Informationsveranstaltung statt. Anbei finden Sie die Videoaufzeichnung der Veranstaltung.

Project progress

We are bringing our IBA processing plant at Nördliche Hafenstraße 3a up to the latest technological standards!
To achieve this, we are building a new processing plant and completely reorganizing the storage areas of our IBA heaps. Our goal: The new plant will significantly improve the efficiency of filtering metals from the IBA – a crucial contribution to the recovery of raw materials such as rare earths and metals. Furthermore, we are improving the environmental and health impact for our employees and local residents: less noise, less dust, and better protection of groundwater.

The overall project is divided into two construction phases: First, we are building a new storage area at Nördliche Hafenstraße 8 (construction start: May 2026). In the second phase, we plan to construct a new processing hall to replace the existing facility at Nördliche Hafenstraße 3a. The new facility is scheduled to be commissioned in 2027.

The project in numbers

The “Repowering Würzburg” project improves safety, environmental protection, health and technology – the most important facts and figures at a glance.

250.000t

Production volume per year

Max. 180.000t

Storage quantity

>20Mil.

Project volume in EUR

new situation Old situation Old situation new situation

Swipe left or right to compare

Our mission: From old to new - modernisation at the Würzburg site

With the planned renovation and new construction at our Würzburg site, we will also implement our mission regionally. The plant will contribute to the efficient processing of mineral residues from industrial processes, save CO2, and thus contribute to the regional circular economy.

Reduction of emissions

New dust extraction technology, modern facilities and less factory traffic reduce dust
and noise emissions in the new Würzburg harbor and the surrounding area.

Protection of people and the environment

Modern storage facilities protect soil and groundwater and contribute to a better environment and quality of life in Würzburg.

More safety in the workplace

Optimized operational processes, modern facilities and less factory traffic increase workplace safety for our employees.

FAQ: Your questions – our answers

Here you will find answers to frequently asked questions about the "Repowering Würzburg" project.

About the renovation and new construction in Würzburg

  • Where is the facility located?

    In the industrial area of the New Würzburg Port; Nördliche Hafenstraße 3A, 97080 Würzburg.

  • What is happening during the renovation and reconstruction in Würzburg?

    The facility will receive new production and storage areas equipped with state-of-the-art technology.
    Specifically, we divide the project into two construction phases:
    1. Construction of a new storage area (construction phase 1)
    2. Replacement construction of the processing plant at Nördliche Hafenstraße 3a (construction phase 2)
    The replacement hall will be built on an adjacent brownfield site. Existing contaminated land will first be remediated. The old hall will only be demolished once the new one is completed. This will allow operations to continue without major disruption throughout the entire construction period.
    Interruptions will continue while the plant is modernized and renewed step by step. The area of the old hall will then be used as storage space for the plant. The resulting expansion of the company premises will allow for a more efficient structuring of operational processes and traffic, thereby relieving congestion on the surrounding roads.

  • Why are the construction works necessary?

    Modernising the plant will significantly improve metal recovery from the IBA. Furthermore, it will bring the plant's environmental standards up to current technological standards.
    The planned measures will increase workplace safety, reduce emissions, and strengthen the protection of soil and groundwater. In doing so, we will contribute to a better environmental and health quality for our employees and the city of Würzburg.

  • How will the project affect traffic in the new Würzburg port?

    Traffic flow will be significantly improved through the clear separation of car and truck traffic and better route planning. Transport between the stockpiles and the plant will remain entirely on the plant premises, thus relieving congestion on public roads. This increases both safety and operational efficiency.

  • How does modernisation affect the environment and the neighborhood?

    Modernising the plant will significantly improve metal recovery from the IBA. Furthermore, the plant's environmental protection standards will be brought up to current technological standards. An adjacent brownfield site will be remediated of existing contamination and revitalized.
    The planned measures will increase workplace safety, reduce emissions, and strengthen the protection of soil and groundwater. In doing so, we will contribute to a better environmental and health quality for our employees and the city of Würzburg.

  • Will the construction or operation cause any odor, dust, or noise pollution?

    Temporary noise and dust may occur during construction. Once operational, these effects will be significantly reduced through modern technology, dust extraction, and traffic optimization.

  • When will the construction work be completed?

    The first construction phase (storage area) is expected to be completed by the end of 2026. Commissioning of the entire facility is planned for the second quarter of 2027.

  • Where can I find more information about the construction work?

    You can find all information about the project directly with us. Please feel free to contact us if you have any questions. We are also planning a public information event in the summer of 2026 to answer all your questions about the project. Further information will follow shortly on this page.

About the operation of the facilities

  • What is a recycling plant for ash from thermal waste treatment plants?

    A recycling plant for ash from thermal waste treatment plants processes the solid material remaining after thermal waste treatment. During thermal treatment, the waste does not disappear completely; combustion residues, known as "IBA," remain. At Blue Phoenix's processing plant, metals such as copper, gold, silver, and platinum are recovered from these residues and subsequently recycled. The remaining mineral components are processed so that they can be reused as building materials or safely disposed of.

  • What materials are processed here?

    The material processed is primarily municipal solid waste incineration IBA, i.e., IBA from the thermal treatment of municipal solid waste. This is non-hazardous waste, meaning it is not special waste.

  • Does the operation of the plant produce environmentally harmful emissions?

    When the plant is operated properly, no harmful emissions are produced for the environment.
    Blue Phoenix GmbH is a certified waste management company and operates according to the highest environmental standards of German environmental law (KrWG, BImSchG) as well as EU sustainability guidelines and technical environmental standards. These standards ensure that exhaust gases are treated in a controlled manner and pollutants are removed.

  • Is there a risk to groundwater or nature conservation?

    The new storage areas are designed to protect soil and groundwater and minimize risks. This is based in particular on the Federal Water Act (WHG), the Federal Immission Control Act (BImSchG), the Ordinance on Installations for Handling Substances Hazardous to Water (AwSV), and technical regulations such as the Technical Instructions on Air Quality Control (TA Luft). These regulations stipulate, among other things, requirements for impermeable storage areas, containment systems, and control measures to protect the environment and nature.

  • What does Blue Phoenix GmbH do for environmental protection?

    Blue Phoenix GmbH complies with all legal requirements and technical standards. Both internationally and locally at our various locations, our mission is to promote health and environmental protection and emissions reduction. Our top priorities include not only our modern, low-emission facilities, but also the protection and safe working conditions of our employees and open and transparent communication with our local community.

Your contact persons

Dr. Christian Wiegard
Managing Director
Blue Phoenix Deutschland GmbH

Sebastian Schley
Production Manager
Germany

Timo Feis
Operations Management Würzburg

Würzburg headquarters

Krefeld headquarters

Email: